SBS Protected Roof Assembly (typical)

Jump to: navigation, search

SBS Protected Roof Assembly (typical)

Revision as of 20:40, 25 August 2016 by James Klassen (talk | contribs)
To read RoofStar Guarantee Standards for any element in this illustration, click on the blue-linked terms

D1.7.2.jpg


1 WORK INCLUDED

(1) Base Sheet
Adhered to deck using asphalt, cold adhesive, self-adhered, torch applied membrane or loose laid according to manufacturer's specification and to the RoofStar Guarantee Standards.
(2) Base Sheet Flashing
Adhered according to manufacturer's specifications using cold adhesive, self-adhered or torch applied to cover boards, or mechanically attached membrane. Torching directly to wood surfaces is not permitted. Must be carried over to outside of parapet or minimum 200 mm (8") above finished roof surface (see RoofStar Guarantee Standards for SBS Roofing Systems, 10.3).
(3) Cap Sheet
Applied according to manufacturer’s printed instructions and RoofStar Guarantee Standards.
(4) Cap Sheet Flashing
Applied according to manufacturer’s printed instructions and RoofStar Guarantee Standards to top of parapet or minimum 200 mm (8") above top of finished roof surface.
(5) Insulation
See available insulation products in the Accepted Materials section of this Manual.
(6) Filter Fabric
Metal base flashing required. See ;Section 12.
(7) Ballast
Gravel or concrete paving tiles.
(8) Metal Flashing
As required by RoofStar Guarantee Standards.

2 RELATED WORK BY OTHERS

(A) Acceptable Deck
Smooth, dry and clean concrete, coated with proprietary primer.
(B) Plywood Backing
Required on rough concrete or where stripping adhesion is asphalt. Must be primed.
(C) Sloped Wood Blocking
Sloped to roof where parapet is over 100 mm (4") in width.


NOTE: Refer to RoofStar Guarantee Standards for additional requirements.





Back to SBS Application

Back to SBS Construction Details

Back to Construction Details