EPDM Conventionally Insulated System (Typical)
EPDM Conventionally Insulated System (Typical)
(Redirected from EPDM 1.3.1-1 Conventionally Insulated System (mechanically attached))
Division D - Construction Details
EPDM | Conventionally Insulated System (Typical) ( Article 1.1.3.1.)
Notice to Reader | |
Images used in a Construction Detail are representative and not prescriptive, and are not necessarily drawn to scale. They are intended to support the related Standard (Ref. Division A, Article 2.2.1.2.).
The reader may link to the related Article in the detail title, or link to the Standard as it relates to a specific element in the detail. All hyperlinks are displayed blue text. |
EPDM Details
1 WORK INCLUDED
- 1) Gypsum Deck Overlay
- May be required depending on insulation thickness or when required as a thermal barrier by design authority.
- (2) Insulation
- Mechanically attached. Installed according to RoofStar Guarantee Standards. See available insulation products in the Division C of this Manual.
- (3) Single-ply Membrane
- Installed according to manufacturer's instructions and RoofStar Guarantee Standards.
- (4) Adhesive
- Proprietary, installed according to manufacturer's instructions, usually brushed, rolled or sprayed.
- (5) Membrane Flashing
- Adhered according to manufacturer's printed specifications using proprietary adhesive. Must be carried to outside of parapet or minimum 200 mm (8") above finished roof surface.
- (6) Fasteners
- Install according to manufacturer's instructions (style may vary depending on material type and manufacturer's specification).
- (7) Membrane Lap
- EPDM (thermoset) membrane may be joined using uncured tape or proprietary adhesive.
- (8) Metal Cap Flashing
- As required by the RoofStar Guarantee Standards.
2 RELATED WORK BY OTHERS
- (A) Acceptable Deck
- (B) Acceptable Parapet Surface
- Surface must be smooth, dry and clean. Rough surface must be covered with treated plywood, to be determined by design authority or inspector or as required by manufacturer.
- (C) Sloped Wood Blocking
NOTE: See the Standard for additional requirements.
Back to EPDM Construction Details