SBS Fire Separation Joint

Jump to: navigation, search

SBS Fire Separation Joint

Revision as of 15:43, 8 December 2017 by James Klassen (talk | contribs)
RoofStar Guarantee Standards are blue-linked
SBS Details

10.3.4.3.jpg

1 WORK INCLUDED

(1) Gypsum Deck Overlay
If required by design authority.
(2) Vapour Retarder
If required by design authority.
(3) Insulation
See available insulation products in the Accepted Materials section of this Manual.
(4) Insulation Overlay Board
Where required.
(5) Primary Membrane and Membrane Protection
(6) MembraneFlashing
(7) Membrane Counter Flashing
(8) Base Metal Flashing
Mechanically fasten to top of plywood backing. Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.
(9) Metal Flashing / Cladding
(10) Secondary Metal Cap Flashing
Joints to be offset from Cap Flashing, OR Water Channeling Clip may be used (See inset for detail D1.7.19 Roof-Wall Transitions (Fire Separation Wall)), OR solder standing seam joints. Do NOT place combustible materials over top of firewall.
(11) Metal Cap Flashing
Standing seam joints required.

2 RELATED WORK BY OTHERS

(A) Acceptable Deck
(B) Acceptable Wall Surface (Plywood)
(C) Wood Blocking
(D) Grouted Finish
Sloped surface to promote drainage off cap flashing.

NOTE: Refer to RoofStar Guarantee Standards for additional requirements.




Back to RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies

Back to SBS Modified Bitumen Construction Details

Back to Construction Details