Difference between revisions of "SBS Flanged Insert Drain (Clamping Ring)"

Jump to: navigation, search

Difference between revisions of "SBS Flanged Insert Drain (Clamping Ring)"

 
(One intermediate revision by the same user not shown)
Line 14: Line 14:
 
<div style="text-align:center; vertical-align:center">
 
<div style="text-align:center; vertical-align:center">
 
[[File:D1.7.8-3.jpg| link=http://rpm.rcabc.org/images/a/a0/D1.7.8-3.jpg | class=img-responsive]]
 
[[File:D1.7.8-3.jpg| link=http://rpm.rcabc.org/images/a/a0/D1.7.8-3.jpg | class=img-responsive]]
</div>
 
 
::Click below for a printable version of this page.
 
 
<div style="width:150px; text-align: left;">
 
:[[File:Pdf.png|100 px|link=http://rpm.rcabc.org/images/d/d8/D1.7.8-3_Print_Sheet.pdf|'''Print Sheet''']]
 
 
</div>
 
</div>
  
Line 29: Line 23:
 
;(1) [[SBS Roof Systems Standard#PART_5|'''Supporting Deck Overlay''']]: Required when insulation is too thin to span flutes of steel decking or when required as thermal barrier by design authority.
 
;(1) [[SBS Roof Systems Standard#PART_5|'''Supporting Deck Overlay''']]: Required when insulation is too thin to span flutes of steel decking or when required as thermal barrier by design authority.
 
;(2) [[SBS Roof Systems Standard#PART_6|'''Air or Vapour Control Layers''']]: If required by design authority.
 
;(2) [[SBS Roof Systems Standard#PART_6|'''Air or Vapour Control Layers''']]: If required by design authority.
;(3) [[SBS Roof Systems Standard#PART_7|'''Insulation''']]: Mechanically fastened.  See available insulation products in the [[Roof Deck Insulation|'''Accepted Materials''']] section of this Manual.
+
;(3) [[SBS Roof Systems Standard#PART_7|'''Insulation''']]: Mechanically fastened.  See available insulation products in the [[Division C| Accepted Materials]] Division of this ''Manual''.
 
;(4) [[SBS Roof Systems Standard#PART_8|'''Insulation Overlay''']]: Asphalt adhered or mechanically fastened. Two layers required over heat-sensitive insulation.
 
;(4) [[SBS Roof Systems Standard#PART_8|'''Insulation Overlay''']]: Asphalt adhered or mechanically fastened. Two layers required over heat-sensitive insulation.
 
;(5) [[SBS Roof Systems Standard#PART_9|'''Field Base Membrane''']]: Adhered to overlay board using asphalt, cold adhesive, self-adhered, mechanical attachment or torch applied according to manufacturer's specification and to <i>RoofStar Guarantee Standards</i>. Torching directly to wood surfaces is not permitted.
 
;(5) [[SBS Roof Systems Standard#PART_9|'''Field Base Membrane''']]: Adhered to overlay board using asphalt, cold adhesive, self-adhered, mechanical attachment or torch applied according to manufacturer's specification and to <i>RoofStar Guarantee Standards</i>. Torching directly to wood surfaces is not permitted.

Latest revision as of 18:14, 27 October 2023



Division D - Construction Details


SBS | Flanged Insert Drain (Clamping Ring) ( Article 11.3.3.6.)

Notice to Reader
Images used in a Construction Detail are representative and not prescriptive, and are not necessarily drawn to scale. They are intended to support the related Standard (Ref. Division A, Article 2.2.1.2.).

The reader may link to the related Article in the detail title, or link to the Standard as it relates to a specific element in the detail. All hyperlinks are displayed blue text.

SBS Details

D1.7.8-3.jpg


1 WORK INCLUDED

(1) Supporting Deck Overlay
Required when insulation is too thin to span flutes of steel decking or when required as thermal barrier by design authority.
(2) Air or Vapour Control Layers
If required by design authority.
(3) Insulation
Mechanically fastened. See available insulation products in the Accepted Materials Division of this Manual.
(4) Insulation Overlay
Asphalt adhered or mechanically fastened. Two layers required over heat-sensitive insulation.
(5) Field Base Membrane
Adhered to overlay board using asphalt, cold adhesive, self-adhered, mechanical attachment or torch applied according to manufacturer's specification and to RoofStar Guarantee Standards. Torching directly to wood surfaces is not permitted.
(6) Mastic
Compatible mastic accepted by the membrane manufacturer.
(7) Base Membrane Flashing
Adhered according to manufacturer's specifications and to RoofStar Guarantee Standards.
(8) Field Cap Membrane
Applied according to manufacturer's printed instructions and to RoofStar Guarantee Standards.

2 RELATED WORK BY OTHERS

(A) Acceptable Supporting Deck Structure
(B) Clamping Copper Drain
Primed and mechanically fastened. Installed in bed of compatible mastic.
  • Leader size is determined by design authority using the calculation found in the BC Building Code at Appendix P.7.4.10 and Section 7.4.10.11 (Section 7.4.10.10 for gutters) in conjunction with the 15 minute rainfall value from the National Building Code, Appendix C.

NOTE: See the Standard for additional requirements.


Back to "SBS" Roof System Details

Home

© RCABC 2024
No reproduction of this material, in whole or in part, is lawful without the expressed permission of the RCABC Guarantee Corp.