(Created page with "<strong>FOR USE WHEN DISCONNECT OF CABLES OR PIPES IS IMPRACTICAL</strong> <hr> File:6.3.6.1.jpg === WORK INCLUDED === (1) <b>Gypsum Board:</b> Required when insula...")
 
Line 7: Line 7:
  
 
=== WORK INCLUDED ===
 
=== WORK INCLUDED ===
 +
;1) [[RoofStar Guarantee Standards for TPO/PVC Roof Systems#TPOSUBSTRATES|'''Gypsum Deck Overlay''']]: May be required depending on insulation thickness  or when required as a thermal barrier by design authority.
 +
;(2) [[RoofStar Guarantee Standards for TPO/PVC Roof Systems#TPOVAPOUR|'''Vapour Retarder''']]: If required by design authority.
 +
;(3) [[RoofStar Guarantee Standards for TPO/PVC Roof Systems#TPOINSULATION|'''Insulation''']]: Mechanically attached or loose laid for ballasted roof assemblies. Installed according to ''RoofStar Guarantee Standards''. See available insulation products in the [[Roof Deck Insulation|'''Accepted Materials''']] section of this Manual.
 +
;(4) [[RoofStar Guarantee Standards for TPO/PVC Roof Systems#TPOMEMBRANE|'''Single-ply Membrane''']]: Installed according to manufacturer’s instructions and RoofStar Guarantee Standards.
 +
;(5) '''Mastic''': Compatible mastic or sealant.
 +
;(6) [[RoofStar Guarantee Standards for TPO/PVC Roof Systems#TPOSTRIPPING|'''Membrane Flashing''']]: Adhered to curb according to manufacturer's printed specifications using proprietary adhesive.  Must be carried to outside of parapet or minimum 200 mm (8") above finished roof surface. Thermoplastic membrane may be welded or chemically bonded.
  
(1) <b>Gypsum Board:</b> Required when insulation is too thin to span flutes of steel decking (See <i>RGC</i> <i>Guarantee Standard A2.5</i>) or when required as thermal barrier by design authority.
+
<hr>
 
 
(2) <b>Vapor Retarder:</b> If required by design authority.
 
 
 
(3) <b>Insulation:</b> Mechanically attached where deck type permits or loose laid for ballasted roof assemblies. Installed according to <i>RGC</i> <i>Guarantee Standard A4.3. </i>See Section 2.2 for accepted materials.
 
 
 
(4) <b>Single Ply Membrane:</b> Installed according to manufacturer&#8217;s instructions and <i>RGC</i> <i>Guarantee Standards Section 2.1.1 </i>and<i> Section 2.1.3</i>.
 
 
 
(5) <b>Mastic:</b> Compatible mastic or sealant.
 
 
 
(6) <b>Membrane Flashing:</b> Adhered to curb according to manufacturer&#8217;s printed specifications using proprietary adhesive. Thermoplastic membrane may be welded or chemically bonded (See Section 6.2) Thermoset membrane may be joined using uncured tape or proprietary adhesive (See Section 6.1).
 
 
 
  
 
=== RELATED WORK BY OTHERS ===
 
=== RELATED WORK BY OTHERS ===
  
(A) <b>Acceptable Deck</b>
+
;(A) [[RoofStar Guarantee Standards for TPO/PVC Roof Systems#TPODECKS|'''Acceptable Deck''']]
 
+
;(B) [[RoofStar Guarantee Standards for TPO/PVC Roof Systems#TPOWOODBLOCKING|'''Wood Blocking''']]
(B) <b>Wood Blocking</b>
+
;(C) [[RoofStar Guarantee Standards for TPO/PVC Roof Systems#TPO2PIECE|'''Metal 2-Piece Flashing''']]: Assembled around protrusion, laid over compatible sealant on top of primary membrane. Mechanically fasten two components together and fasten flange to wood blocking or deck.
  
(C) <b>Two Piece Flashing:</b> Assembled around protrusion, laid over compatible sealant on top of primary membrane. Mechanically fasten two components together and fasten flange to wood blocking or deck.
 
  
  
'''NOTE''': Refer to <i>RGC Guarantee Standards</i> for additional requirements.
+
'''NOTE''': Refer to '''''RoofStar Guarantee Standards''''' for additional requirements.
  
  

Revision as of 14:46, 9 August 2016

FOR USE WHEN DISCONNECT OF CABLES OR PIPES IS IMPRACTICAL


6.3.6.1.jpg


1 WORK INCLUDED

1) Gypsum Deck Overlay
May be required depending on insulation thickness or when required as a thermal barrier by design authority.
(2) Vapour Retarder
If required by design authority.
(3) Insulation
Mechanically attached or loose laid for ballasted roof assemblies. Installed according to RoofStar Guarantee Standards. See available insulation products in the Accepted Materials section of this Manual.
(4) Single-ply Membrane
Installed according to manufacturer’s instructions and RoofStar Guarantee Standards.
(5) Mastic
Compatible mastic or sealant.
(6) Membrane Flashing
Adhered to curb according to manufacturer's printed specifications using proprietary adhesive. Must be carried to outside of parapet or minimum 200 mm (8") above finished roof surface. Thermoplastic membrane may be welded or chemically bonded.

2 RELATED WORK BY OTHERS

(A) Acceptable Deck
(B) Wood Blocking
(C) Metal 2-Piece Flashing
Assembled around protrusion, laid over compatible sealant on top of primary membrane. Mechanically fasten two components together and fasten flange to wood blocking or deck.


NOTE: Refer to RoofStar Guarantee Standards for additional requirements.





Back to TPO/PVC Application

Back to TPO/PVC Construction Details