SBS | Metal Edge Termination ( Article 10.3.4.2.)

Notice to Reader
Images used in a Construction Detail are representative and not prescriptive, and are not necessarily drawn to scale. They are intended to support the related Standard (Ref. Division A, Article 2.2.1.2.).

The reader may link to the related Article in the detail title, or link to the Standard as it relates to a specific element in the detail. All hyperlinks are displayed blue text.

SBS Details


Part 10 - Construction Detail - Metal Edge Termination - SBS.png

1 WORK INCLUDED

(1) Suitable field substrate
May be the roof deck or deck overlay (if an uninsulated system), or insulation and an overlay (if conventionally insulated).
(2) Primer or adhesive
For self-adhered or adhered membranes, as required by the manufacturer.
(3) Field Base Sheet Membrane
Selected to conform to the requirements in Membrane Composition, Thickness, and Selection Table 9.2.1.1. and conforming to the options or requirements in a Tested Assembly, an Assembly with Proven Past Performance, or a custom-engineered assembly. Carried continuously over the outside edge and down the vertical face at least 50.8 mm (2”), or 50.8 mm past any cold joint.
(4) Sealant or mastic
Applied to field base sheet membrane, beneath metal edge flashing.
(5) Metal edge (flush) flashing
Fasteners spaced no more than 203.2 mm (8”) on the top face in two offsetting rows.
A hemmed drip edge (shown) is required (Refer to Article 13.2.2.1. for fabrication requirements).
(6) Membrane flashing strip
Applied to the metal edge flashing and overlapping onto the field membrane at least 101.6 mm (4”). Prime when required by the manufacturer (primer illustrated).
(7) Field Cap Sheet Membrane
Selected to conform to the requirements in Membrane Composition, Thickness, and Selection Table 9.2.1.1. and conforming to the options or requirements in a Tested Assembly, an Assembly with Proven Past Performance, or a custom-engineered assembly. Installed according to Part 9 requirements.
(8) Edge mastic
Apply mastic or another membrane-compatible sealant to the outer exposed edge of the field cap sheet membrane. Coat with granules.

2 RELATED WORK BY OTHERS

(A) Supporting (Structural) Roof Deck
Generic and representative only.
(B) Roof edge substrate
Wood blocking, required for conventionally insulated roofs.
(C) Wall assembly
Generic and representative only.

NOTE: See the Standard for additional requirements.