SBS Expansion Joint (Wall)

Jump to: navigation, search

SBS Expansion Joint (Wall)

Revision as of 17:06, 27 August 2021 by James Klassen (talk | contribs)

RoofStar Guarantee Standards are blue-linked
SBS Details

10.3.3.2.jpg


Click below for a printable version of this page.
Print Sheet

1 WORK INCLUDED

(1) Air or Vapour Control Layers
The requirement for a vapour retarder is determined by the design authority. Optional terminations.
(2) Insulation
(3) Insulation Overlay
Where required.
(4) Primary Membrane and Membrane Protection
(5) Membrane Flashing
Mechanically fasten to top of wood blocking.
(6) Membrane Counter-flashing
Flashing sealed to wall with compatible mastic.
(7) Metal Base Flashing
Mechanically fasten to top of wood blocking (C). Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.
(8) Metal Counter-flashing
Into reglet approximately 30 mm (1¼") and caulked.
(9) Caulking
(10) Membrane Underlay
Minimum self-adhered modified bitumen membrane.
(11) Metal Cap Flashing
Must overlap exterior wall finish. Fasten with continuous concealed clip-type fasteners or cladding screws evenly spaced between seams.

2 RELATED WORK BY OTHERS

(A) Acceptable Supporting Deck Structure
(B) Air and Vapour Control Layer Seal
Sealed to wall.
(C) Wood Blocking
Height to provide minimum 200 mm (8") above completed roof system, slope top edge.
(D) Flexible Insulation
(E) Reglet
(F) Sloped Wood Blocking

NOTE: See the Standard for additional requirements.


Back to RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies

Back to SBS Modified Bitumen Construction Details

© RCABC 2024
No reproduction of this material, in whole or in part, is lawful without the expressed permission of the RCABC Guarantee Corp.