Difference between revisions of "ASM Cylindrical Penetration (Flexible Boot Flashing)"
Difference between revisions of "ASM Cylindrical Penetration (Flexible Boot Flashing)"
Line 11: | Line 11: | ||
<div class="col-md-6"> | <div class="col-md-6"> | ||
<div style="text-align:center; vertical-align:center"> | <div style="text-align:center; vertical-align:center"> | ||
− | [[File:8.1.4.8.1.jpg|class=img-responsive]] | + | [[File:8.1.4.8.1.jpg| link=http://rpm.rcabc.org/images/7/77/ASM_11.1.1.jpg | class=img-responsive]] |
</div> | </div> | ||
::Click below for a printable version of this page (N/A) | ::Click below for a printable version of this page (N/A) |
Revision as of 22:12, 31 August 2021
Notice to Reader | |
Images used in a Construction Detail are representative and not prescriptive. Nor are they necessarily drawn to scale. Rather, they are provided to visually convey the requirements of the Standard they represent. Unless otherwise required by the Standard, dimensions, the selection of materials and their application remains the responsibility of the Design Authority. The full text of the referenced requirements in the Standard may be read by using the blue hyperlinks |
ASM Details
1 WORK INCLUDED
- (1) Underlayment
- The type of underlay required is determined by roof slope.
- (2) Insulation
- Offset and stagger layers 300 mm (12").
- (3) Vapour-permeable separation membrane
- Installed over insulation and required on all insulated Architectural Sheet Metal Roof Systems. The material must be located between the insulation and metal panels/ventilation material (see 8.1.2 Design).
- (4) Ventilation layer
- A ventilation space is required on slopes less than 1:3; entangled mesh (shown) may be used as void fill. The ventilation space facilitates drying as condensation forms on the underside of the metal panels.
- (5) Architectural Metal Roof Panel
- Clips not illustrated.
- (6) to (10) Pipe Boot
-
- Set in two continuous beads of acceptable sealant.
- Secured with high-domed gasketed cladding-type screws.
- Clamped to penetration with a stainless steel drawband.
- Sealed between flashing and penetration.
- (11) Water-tight storm collar
- Installed by other trade (new construction only) or as required in this Standard. See 11.3.3 (5).
2 RELATED WORK BY OTHERS
- (A) Pipe penetration
NOTE: See the Standard for additional requirements.
Back to ASM Roof System Details