<big><big>Division D - Construction Details</big></big>
 
<big><big>Division D - Construction Details</big></big>
 
<hr>
 
<hr>
<big><big><big><big><big>ASM 10.2.2 Roof-Headwall Connection (Vented)</big></big></big></big></big>
+
<big><big><big><big><big>ASM | Roof-Wall Connection (Head-wall, Vented) ([[ASM_Roof_Systems_Standard#10.3.2.3. General Application Requirements for Perimeters and Walls | Article 10.3.2.3.]])</big></big></big></big></big>
{| class="wikitable" | style="color: black; background-color: orange; width: 100%;text-align:center"
+
{{Template:Construction Details Header}}
| colspan="2"  | <big>'''''Notice to Reader'''''</big>
 
|-
 
| style="color: black; background-color: #ffffcc; width: 100%;text-align:center" | Images used in a Construction Detail are representative and not prescriptive.  Nor are they necessarily drawn to scale. Rather, they are provided to visually convey the requirements of the Standard they represent. Unless otherwise required by the Standard, dimensions, the selection of materials and their application remains the responsibility of the ''Design Authority''.<br><br>The full text of the referenced requirements in the [[ASM Roof Systems Standard | '''Standard''']] may be read by using the <span style="color:#6495ed">'''blue hyperlinks'''</span>
 
|}
 
 
 
  
 
<div class="panel panel-success">
 
<div class="panel panel-success">
Line 31: Line 26:
 
<div class="col-md-6">
 
<div class="col-md-6">
 
=== WORK INCLUDED ===
 
=== WORK INCLUDED ===
;(1) [[ASM Roof Systems Standard#ASMUNDERLAYMENT|'''Underlayment''']]: Applicable for all Architectural Sheet Metal systems.  For slopes less than 1:3, the entire roof slope must be covered with a <u>self-adhered</u> underlayment.
+
;(1) [[ASM Roof Systems Standard#PART_8|'''Underlayment''']]: Applicable for all Architectural Sheet Metal systems.  For slopes less than 1:3, the entire roof slope must be covered with a <u>self-adhered</u> underlayment.
;(2) [[ASM Roof Systems Standard#ASMSEP-VENT|'''Ventilation material''']]: A ventilation space is required on slopes less than 1:3; entangled mesh (shown) may be used as void fill.  The ventilation space facilitates drying as condensation forms on the underside of the metal panels.
+
;(2) [[ASM Roof Systems Standard#PART_8|'''Ventilation material''']]: A ventilation space is required on slopes less than 1:3; entangled mesh (shown) may be used as void fill.  The ventilation space facilitates drying as condensation forms on the underside of the metal panels.
;(3) [[ASM Roof Systems Standard#ASMCLIP|'''Metal Panel Clip''']]: Installed to metal roof panel manufacturer's printed instructions.
+
;(3) [[ASM Roof Systems Standard#PART_9|'''Metal Panel Clip''']]: Installed to metal roof panel manufacturer's printed instructions.
 
;(4) Bearing plate: Used to support clips and distribute dead and live loads when direct contact with a solid substrate is not possible.
 
;(4) Bearing plate: Used to support clips and distribute dead and live loads when direct contact with a solid substrate is not possible.
;(5) [[ASM Roof Systems Standard#ASMPANEL |'''Architectural metal roof panel''']]
+
;(5) [[ASM Roof Systems Standard#PART_9 |'''Architectural metal roof panel''']]
;(6) [[ASM Roof Systems Standard#ASMZ |''''Z'-Closure''']]: Set in acceptable sealant and secured with compatible, non-corrosive, flat head fasteners.
+
;(6) [[ASM Roof Systems Standard#PART_10 |''''Z'-Closure''']]: Set in acceptable sealant and secured with compatible, non-corrosive, flat head fasteners.
 
;(7) Perforated ventilation metal: Mechanically fastened to wall and 'Z'-closure.  The outer edge serves as a hook for the roof-wall metal flashing.
 
;(7) Perforated ventilation metal: Mechanically fastened to wall and 'Z'-closure.  The outer edge serves as a hook for the roof-wall metal flashing.
;(8) [[ASM Roof Systems Standard#ASMSHEETMETAL |'''Sheet Metal Flashing''']]: Hooked to perforated ventilation metal and fastened to wall with non-corrosive, flat head fasteners 300 mm (12") o/c or preformed foam closures set in acceptable sealant with high domed gasketed cladding type screws at each standing rib.  
+
;(8) [[ASM Roof Systems Standard#PART_10 |'''Sheet Metal Flashing''']]: Hooked to perforated ventilation metal and fastened to wall with non-corrosive, flat head fasteners 300 mm (12") o/c or preformed foam closures set in acceptable sealant with high domed gasketed cladding type screws at each standing rib.  
;(9) [[ASM Roof Systems Standard#ASMCOUNTER |'''Metal Counter Flashing''']]: Must extend behind wall system and wall control layers. Stucco stops are not considered to be a counter flashing.
+
;(9) [[ASM Roof Systems Standard#PART_13 |'''Metal Counter Flashing''']]: Must extend behind wall system and wall control layers. Stucco stops are not considered to be a counter flashing.
  
 
<hr>
 
<hr>
  
 
=== RELATED WORK BY OTHERS ===
 
=== RELATED WORK BY OTHERS ===
;(A) [[ASM Roof Systems Standard#ASMDECK|'''Acceptable deck''']]
+
;(A) [[ASM Roof Systems Standard#PART_2|'''Acceptable deck''']]
 
;(B) '''Wall control layers''': must be positively lapped with roof materials and flashings, to maintain continuity across systems.
 
;(B) '''Wall control layers''': must be positively lapped with roof materials and flashings, to maintain continuity across systems.
 
;(C) '''Wall cladding''':
 
;(C) '''Wall cladding''':

Latest revision as of 17:31, 28 June 2022



Division D - Construction Details


ASM | Roof-Wall Connection (Head-wall, Vented) ( Article 10.3.2.3.)

Notice to Reader
Images used in a Construction Detail are representative and not prescriptive, and are not necessarily drawn to scale. They are intended to support the related Standard (Ref. Division A, Article 2.2.1.2.).

The reader may link to the related Article in the detail title, or link to the Standard as it relates to a specific element in the detail. All hyperlinks are displayed blue text.

ASM Details

ASM 10.2.2 Roof-Headwall Connection (Vented).jpg

Click below for a printable version of this page (N/A)
Print Sheet

1 WORK INCLUDED

(1) Underlayment
Applicable for all Architectural Sheet Metal systems. For slopes less than 1:3, the entire roof slope must be covered with a self-adhered underlayment.
(2) Ventilation material
A ventilation space is required on slopes less than 1:3; entangled mesh (shown) may be used as void fill. The ventilation space facilitates drying as condensation forms on the underside of the metal panels.
(3) Metal Panel Clip
Installed to metal roof panel manufacturer's printed instructions.
(4) Bearing plate
Used to support clips and distribute dead and live loads when direct contact with a solid substrate is not possible.
(5) Architectural metal roof panel
(6) 'Z'-Closure
Set in acceptable sealant and secured with compatible, non-corrosive, flat head fasteners.
(7) Perforated ventilation metal
Mechanically fastened to wall and 'Z'-closure. The outer edge serves as a hook for the roof-wall metal flashing.
(8) Sheet Metal Flashing
Hooked to perforated ventilation metal and fastened to wall with non-corrosive, flat head fasteners 300 mm (12") o/c or preformed foam closures set in acceptable sealant with high domed gasketed cladding type screws at each standing rib.
(9) Metal Counter Flashing
Must extend behind wall system and wall control layers. Stucco stops are not considered to be a counter flashing.

2 RELATED WORK BY OTHERS

(A) Acceptable deck
(B) Wall control layers
must be positively lapped with roof materials and flashings, to maintain continuity across systems.
(C) Wall cladding

NOTE: See the Standard for additional requirements.


Back to ASM Roof System Details

Home

© RCABC 2024
RoofStarTM is a registered Trademark of the RCABC.
No reproduction of this material, in whole or in part, is lawful without the expressed permission of the RCABC Guarantee Corp.