:A membrane moisture scan survey and report that confirms the water tight integrity of waterproofing systems is a '''mandatory''' requirement of the RoofStar Guarantee Program for all waterproofing systems, prior to installation of overburdens or wearing courses. Membrane moisture survey scans must be performed by an independent moisture detection company, whose moisture detection system has been reviewed by the RCABC Technical Committee and deemed to be suitable for inclusion in the RoofStar Guarantee Program (Waterproofing). In addition, moisture monitoring sensor grids (conductance scanning grid) are <b>mandatory</b> and shall be installed on the top surface of all waterproofing membrane systems designed with inaccessible overburdens and wearing courses. The exceptions that do not require moisture monitoring sensor grids are pavers on pedestals and gravel ballast to a maximum 100mm (4") thick . Moisture monitoring sensor grids<b> shall </b>be installed prior to installation of overburdens or wearing courses and may be placed over protection boards or SBS membranes that have been set in hot fluid-applied modified asphalt.
 +
 +
:'''Note''':
 +
:Flood Testing is <b>not a recommended practice</b> but is at the discretion of the design authority or owner. If flood testing is required to water test waterproofing membranes, testing shall be conducted prior to installation of insulation and overburdens and be performed to ASTM D5957 - 98.
 
{{Template:Materials - Leak Detection & Monitoring Systems}}
 
{{Template:Materials - Leak Detection & Monitoring Systems}}
  

Latest revision as of 22:45, 9 November 2016

Accepted Materials for a RoofStar Guarantee

The tables and products shown below provide basic material data and links to more information about the materials, including manufacturers' published Technical Data sheets, but this information is not intended for use as a comparison of material performance or quality. It is the sole responsibility of the Design Authority to assess the performance capability and material suitability for specific design requirements.

The materials listed are those which have been accepted by the RoofStar Guarantee Program (RCABC Guarantee Corp., or RGC) for use in a roof or grade-level waterproofing system that will qualify for a RoofStar Guarantee. The acceptance of these materials by the RGC (RoofStar Guarantee Program) in no way reflects on the quality or performance of other materials not listed.

The materials and guideline specifications are listed under the name of the manufacturer and/or supplier of the primary membrane material, with the exception of BUR membranes for which the reader will find RoofStar Guarantee Program guidelines on traditional built-up roofing systems (BUR) incorporating organic and glass felt primary membranes.

A membrane moisture scan survey and report that confirms the water tight integrity of waterproofing systems is a mandatory requirement of the RoofStar Guarantee Program for all waterproofing systems, prior to installation of overburdens or wearing courses. Membrane moisture survey scans must be performed by an independent moisture detection company, whose moisture detection system has been reviewed by the RCABC Technical Committee and deemed to be suitable for inclusion in the RoofStar Guarantee Program (Waterproofing). In addition, moisture monitoring sensor grids (conductance scanning grid) are mandatory and shall be installed on the top surface of all waterproofing membrane systems designed with inaccessible overburdens and wearing courses. The exceptions that do not require moisture monitoring sensor grids are pavers on pedestals and gravel ballast to a maximum 100mm (4") thick . Moisture monitoring sensor grids shall be installed prior to installation of overburdens or wearing courses and may be placed over protection boards or SBS membranes that have been set in hot fluid-applied modified asphalt.
Note:
Flood Testing is not a recommended practice but is at the discretion of the design authority or owner. If flood testing is required to water test waterproofing membranes, testing shall be conducted prior to installation of insulation and overburdens and be performed to ASTM D5957 - 98.
Click on a manufacturer's name to see the full list of their products accepted for use in the RoofStar Guarantee Program
Manufacturer Product & Service Recognized Applications
Detec Systems Ltd. Integrity Scans, Static and Monitored Electronic Leak Detection systems PMR, MPMR, Waterproofing (Grade-level)
International Leak Detection (ILD) Integrity Scans, Static and Monitored Electronic Leak Detection systems PMR, MPMR, Waterproofing (Grade-level)