ASM 6.3.1 Air and Vapour Controls (field)
ASM 6.3.1 Air and Vapour Controls (field)
Revision as of 14:11, 31 August 2021 by James Klassen (talk | contribs) (Created page with "{{Template:RPM Info}} <hr> {| class="wikitable" | style="color: black; background-color: orange; width: 100%;text-align:center" | colspan="2" | <big>'''''Notice to Reader''''...")
Notice to Reader | |
Images used in a Construction Detail are representative and not prescriptive. Nor are they necessarily drawn to scale. Rather, they are provided to visually convey the requirements of the Standard they represent. Unless otherwise required by the Standard, dimensions, the selection of materials and their application remains the responsibility of the Design Authority. The full text of the referenced requirements in the Standard may be read by using the blue hyperlinks |
"All Systems" Details
- Click below for a printable version of this page (under development)
1 WORK INCLUDED
- (1) Supporting Deck Overlay
- Recommended over steel decks, to provide continuous support for membrane control layers (this fulfills the requirement for continuity, British Columbia Building Code, Div. B, 5.4.1.2 (3)).
- (2) Air or Vapour Controls
- Self-adhering membrane (typical).
- (3) Metal Support
- For fully or intermittently unsupported side or end laps. Use pre-finished galvanized steel (min. 24 Ga.), fabricated at least 100 mm (4”) wider than membrane overlaps, and secured with compatible flat-head fasteners (two fasteners per flute, or as otherwise specified).
- (4) Long edges
- Centre membrane runs along top flutes of steel deck (applicable when no deck overlay is specified and installed).
- (5) End laps
- Overlap the roll ends at least 100 mm (4”), or as specified by the membrane manufacturer (whichever is greater). End laps must be fully supported by the roof deck or a metal support.
- (6) Side laps
- Overlap membrane side laps at least 50 mm (2”), or as specified by the membrane manufacturer (whichever is greater). Side laps must be fully supported by the roof deck or a metal support.
2 RELATED WORK BY OTHERS
- (A) Acceptable Deck
NOTE: See the Standard for additional requirements.